It is not clear to us if article 7 is referring to “first round”, “second round” or the entire project. Is it possible for the client to stop the work and to hand the project to other consultants without paying a compensation fee during all phases/”rounds”?.

Could it be possible to receive clarification regarding Article 7?

The article 7 refers to the rounds of this competition. If the competition is terminated prematurely, the participants will receive compensation pursuant to clause 18.3 of the competition regulations.

Article 7 provides for the extent of the copyright rights to the work produced in the first and second round of the competition and it must be allowed that the copyright to the urban concept is transferable to the developer.